  • 1. Buan factory solar power plant
    • capacity : 1.127 megawatt
    • area : 12,000 square meter
    • location : Our company’s buan factory, 29 buannonggongdanji-gil, haenanmyeon, buan-gun, Jeonlabuk-do, Korea
    • 설supplying voltage, Hz, electrical power room quantity : 22,900 v, 60hz, 1
    • operation date : Jun. 30th. 2014
  • 2. ‘Korean army’ solar power plant project (ongoing)
    • planned capacity : 6 megawatt
    • cooperative company : Buhung solar co.,ltd.
    • planned location : Korean army force in Kyeonggi-do and gangwon-do
    • planned construction start : Sep. 2014.
  • 3. ‘Province unit’ solar power plant project (ongoing)
    • planned capacity : 40 megawatt
    • cooperative company : Buhung solar co.,ltd.
    • planned business area : Jeonllanam-do
    • planned construction start : in 2014. now, feasibility study for construction start is progressing.